Georgette is upgrading the infrastructure of the site to meet local requirements:
- Completing a fence across the top of the campus;
- Upgrading the well that was installed in 2014;
- Completing the electrification of the site.
Regarding the fence:
The Education Department of Kinshasa requires that schools are completely enclosed in a fence, with metal gates. The German church provided partial funding for this fence. Three sides are completed.
There is about seventy-five meters more required along the road – the brown/sand line across the top of the schoolyard. Also, two gates are required – one for pedestrians only, and another to allow service vehicles in.
The cost of completing this properly is approximately $30,000. The cost is higher than we’d expect, for the following reasons:
- this part of Kinshasa sits on large sand dunes, so the foundations must be well-built;
- the fences in this area are made of stone or bricks. Wood is quickly eaten by insects, doesn’t stand up to the elements well, and is also very expensive. It is used almost entirely in finishing applications, not construction;
- and the gates are made of metal, welded together. The cost to Georgette is somewhat reduced by having one of her graduates provide welding expertise at a steep discount.
Regarding the well:
A 110 meter borehole was installed in 2014, and the equipment needs an upgrade at this point. More details will be available after our visit there the first week of June. Our current estimate is that this will cost $10,000.
Regarding electricity on site:
Georgette recently received a donation to partially complete the electricity project on-site, and needs another $2,000 to complete that project, at which point her current needs will be met.